Three time’s a charm for KCCJ

KCCJ installed this Falcon F900 suite in 48 hours at The Clayton Hotel.

Dartford-based kitchen design house KCCJ has been called upon to assist with the refurbishment of another area of the production kitchen within Leeds’ largest hotel.

This is the third time in the last 12 months that the distributor has assisted The Clayton Hotel, part of the Dalata Hotel Group.

Last year KCCJ replaced a chilled prep area followed by a large dishwash facility.

Story continues below

2018’s work comprised removing the old island cooking suite and replacing with a range of Falcon F900 equipment. At the same time, upgrades to the extraction and supply air systems including new fans were also made.

The latest project was completed within 48 hours.

KCCJ reported that the old suite was “literally cut to pieces” in order to get it out of the kitchen, with alterations to the gas and electrics taking place simultaneously and then the new equipment installed the following day.